Projects monitored
Investment projects from adopted budgets, visited by citizens with geotagged photos.
You know a project funded by your Province, City or Municipality that is not listed? Report it: it will be checked, then you can follow how it is carried out and report problems if there are any.
0%
Results
Average progress
Average progress of all the projects: a planned project counts as 0 %, a completed one as 100 %; checked during visits.
- Completed0%
- Visited on the ground0%
- projects monitored
- 542
- total investment
- 180,0 bn CDF
- completed projects (value)
- —
- past their end date
- 1
- stalled or abandoned
- 0%
- field visits
- 1
- Cities and Municipalities
- 5
- sectors
- 12
542 projects
-
Réhabilitation de la micro-centrale hydroélectrique de Katchungu (Shabunda)
Katchungu, Shabunda —
Planned0 %
-
Projet de réhabilitation et extention de neuf micro centrales hydro-électrique Coût Total : 988.831.472Fc. Prévisions 2025 ci-contre
Province du Sud-Kivu 988,8 M CDF
Planned0 %
-
Projet de Construction de dix micro centrales hydroélectriques Coût Total : 1.730.455.074Fc. Prévisions 2025 ci-contre
Province du Sud-Kivu 1,7 bn CDF
Planned0 %
-
Projet de construction de 15 micro centrale solaire Coût Total : 2.155.852.606Fc. Prévisions 2025 ci-contre
Province du Sud-Kivu 2,2 bn CDF
Planned0 %
-
Acquisition des mobiliers, équipements de bureau pour le Cabinet du Ministre; la DPMER et la Cellule Provinicial de Codification
Province du Sud-Kivu 67,0 M CDF
Planned0 %