Projects

Public building · Affaires sociales, genre et jeunesse

Construction de la clôture du terrain de Burhinyi (Mwenga)

Burhinyi, Mwenga, Province du Sud-Kivu
Budget 2025

Planned

Assess this project Report a problem

Public building
  • physical progress
  • 12,9 M FCplanned cost
  • —of the budget line paid
  • 0problems found
  • 0monitoring visits

How is the project going?

0 problems · 0 points in order, from the latest visits

Physical progress0 %
Time elapsed—

No monitoring visit published yet for this project.

Assess this project

One form for this public building, in three parts: the project visit, the building site and the questions specific to this type of infrastructure. Geotagged photos are required; a proof can be added under each answer.

  1. Monitoring an investment project 8 questions

    Site visit: does the project exist, is work progressing, is the quality acceptable and is it being used? Geotagged photos are required.

  2. Building-site monitoring 14 questions

    On every building site: contract and bill of quantities shown, site board, materials, safety, payments and signs of corruption.

  3. Public building 7 questions

    Building as planned, quality of roof and walls, water and power, latrines, accessibility, furniture, actual use.

Log in to assess29 questions in all

Do you live here and want to keep an eye on this budget? Become a community monitor →

Survey of the direct beneficiaries

Interviews of the people the project is meant to serve: need, consultation, usefulness, who to contact, money asked for, quality, satisfaction. One form per person, without name or contact.

Not enough answers yet (0 of 5 needed before publication).

Log in to assess

Latest visits

No monitoring visit published yet for this project.