On 17 October 2026, heavy rain caused runoff water to overflow onto the diversion built under the new bridge over the Kavimvira river. The abutment of the old railway bridge tilted and traffic was cut off between Kavimvira and Mulongwe: bajaj, taxis, buses and motorbikes could no longer get through, and only pedestrians could cross.

RN5, déviation sous le nouveau pont de la rivière Kavimvira, Kavimvira Municipality · Received on 17/10/2026 · DS-2026-00015

Being handled Urgent

Report the same problem Track my request Map

Roads, bridges and streets
  1. Received17/10/2026
  2. Taken in charge18/10/2026
  3. ResolvedWaiting
  • 25days since the request
  • 27 hto be taken in charge
  • —to be resolved
  • —resident’s satisfaction

What was reported

On 17 October 2026, heavy rain caused runoff water to overflow onto the diversion built under the new bridge over the Kavimvira river. The abutment of the old railway bridge tilted and traffic was cut off between Kavimvira and Mulongwe: bajaj, taxis, buses and motorbikes could no longer get through, and only pedestrians could cross.

Translated by the AI assistant.

Original text

Le 17 octobre 2026, une forte pluie a fait déborder les eaux de ruissellement sur la déviation aménagée sous le nouveau pont de la rivière Kavimvira. La culée de l’ancien pont ferroviaire s’est inclinée et la circulation a été coupée entre Kavimvira et Mulongwe : bajaj, taxis, bus et motos ne passaient plus, seuls les piétons pouvaient traverser.

Reported by Dalili B. John

What the City did

  1. 18/10/2026 10:00 · Being handled

    Le chef de chantier de l’entreprise EIS-EKA a promis au Maire de rétablir le passage avec des engins le 18 octobre avant 13 h.

  2. 17/10/2026 07:00 · Received

    Problème signalé par Dalili B. John (veille citoyenne par Initiative pour la Gouvernance de Proximité, CERC).